Decision on Padma funding after talks with Japan govt: Jaica
Japan International Cooperation Agency (Jaica), another co-financer of Padma bridge project, in a statement on Monday said it would take decision on the project after having a discussion with Japan government.
Jaica’s formal statement came two days after the leading financer of the project World Bank cancelled its $1.2 billion credit for the project claiming to have proof of a corruption conspiracy involving Bangladeshi officials, executives of a Canadian firm and private individuals.
Jaica was committed to funding $400 million for the Padma bridge project.
As Finance Minister AMA Muhith was telling Parliament on Monday the government will sit with the World Bank any time to end the impasse over Padma bridge funding, Japan International Cooperation Agency (JICA) said that it will continue with funding the project.
The announcement came hours after Asian Development Bank (ADB) hinted its withdrawal from the coveted project following World Bank s withdrawal.
“Our position has not been changed. We hope that the government of Bangladesh will deal with the current issues in a constructive way,” JICA’s Public Relations Office in Dhaka said in a statement.
The Finance Minister told Parliament that the government was determined to start construction of $ 2.9 billion Padma bridge in the current fiscal and it will engage the top leadership of the World Bank any time to break the impasse.
The minister made the remarks while delivering speech on Padma bridge after the bank on June 30 cancelled the loan agreement, which makes Bangladesh’s biggest infrastructure project yet uncertain.
“We are also continuously negotiating with the influential members of the World Bank,” he said.
“Our Executive Director in the World Bank is holding talks with the (top officials).”
Earlier in the morning, ADB issued a statement saying, “ADB understands and respects the reasons that have led the World Bank to its decision.”
“ADB and the World Bank follow similar policies, rules and procedures on governance and fiduciary oversight,” said the statement indicating ADB’s stance in favour of the WB.
ADB pledged US$ 610 million for the project and JICA US$ 400 million.
THE FEASIBILITY STUDY OF PADMA BRIDGE
|
Study team : Japan International Cooperation Agency (JICA)
Start : May 2003, END : March 2005
Timing of SubmissionMain Contents
Inception Report
Progress Report 1
Interim Report
– Results of IEE and SIA
– Decision of the Bridge Location
Progress Report 2
-Comparative analysis, preliminary design and construction plan
Draft Final Report
Final Report
Site-1 | : | Paturia-Goalundo |
Site-2 | : | Dohar-Charbhadrasan |
Site-3 | : | Mawa-Janjira |
Site-4 | : | Chandpur-Bhedarganj |
Findings of the Interim report Basic Policy of the Feasible Study:
|
|||||||||||||||||||||||||
|
Main Function of Padma Bridge | ||||||||||||||||||||||||
|
Location of Padma Bridge | ||||||||||||||||||||||||
|
Socio-Economic Impacts of Padma Bridge | ||||||||||||||||||||||||
|
Associated Road Development Project | ||||||||||||||||||||||||
|
Associated Road Development Project | ||||||||||||||||||||||||
|
Impact of Macro Balance of the Country | ||||||||||||||||||||||||
|
Private Sector Participation | ||||||||||||||||||||||||
Study Items completed by Progress Report (1) | |||||||||||||||||||||||||
|
Collection & Review of Existing Data, Information and Reports related to the Study | ||||||||||||||||||||||||
|
Identification of Conceivable Bridge Crossing Sites | ||||||||||||||||||||||||
|
Traffic Survey & Traffic Demand Forecast | ||||||||||||||||||||||||
|
Preliminary River Study | ||||||||||||||||||||||||
|
Preliminary Technical Consideration of Highway & Bridge Planning | ||||||||||||||||||||||||
|
Preliminary Environment & Social Condition | ||||||||||||||||||||||||
|
Screening of Alternatives | ||||||||||||||||||||||||
|
|||||||||||||||||||||||||
The Study Items completed by Interim Report |
|
||||||||||||||||||||||||
Engineering Survey | |||||||||||||||||||||||||
Preliminary River Facility Design | |||||||||||||||||||||||||
Preparatory Preliminary Study for Bridge & Highway | |||||||||||||||||||||||||
IEE | |||||||||||||||||||||||||
SIA & Resettlement Issue | |||||||||||||||||||||||||
Economic Effect & Preliminary Feasibility | |||||||||||||||||||||||||
Findings from Geotechnical Investigation | |||||||||||||||||||||||||
Difference of Subsoil Conditions between 2 Sites | |||||||||||||||||||||||||
N-values of SPT at Mawa-Janjira site are higher than those at Paturia-Goalundo site. | |||||||||||||||||||||||||
Horizontal Ground Reaction | |||||||||||||||||||||||||
As the coefficients of horizontal ground reaction in the bored holes showed relatively smaller values, such characteristics would have to be considered in the preliminary design of foundations.
|
|||||||||||||||||||||||||
Liquefaction | |||||||||||||||||||||||||
Paturia-Goalundo site has high potential risks of liquefaction when sever earthquake takes place. On the other hand, Mawa – Janjira site has lesser potential risks of the same.
|
|||||||||||||||||||||||||
Finding (1 ) | |||||||||||||||||||||||||
N -values of SPT at Mawa-Janjira site are higher than those at Paturia-Goalundo. Main reason of this result might come from the subsoil composition at Paturia – Goalund that consists of relatively singular particle size distribution of fine sand. | |||||||||||||||||||||||||
Finding (2) | |||||||||||||||||||||||||
Below maximum scour levels El -40m PWD, N-values of SPT at Mawa-Janjira are higher than those at Paturia-Goalundo. | |||||||||||||||||||||||||
Finding (3) | |||||||||||||||||||||||||
From the pressure – meter tests in situ bored holes, the following relation was obtained: | |||||||||||||||||||||||||
Em=4.52N | |||||||||||||||||||||||||
Where, N:N-value of SPT | |||||||||||||||||||||||||
Em: Coefficient of horizontal ground reaction | |||||||||||||||||||||||||
Ref.: Em+7N…..Design specification of Highway Bridges adopted by JRA. | |||||||||||||||||||||||||
Em=7n | |||||||||||||||||||||||||
Finding (4) | |||||||||||||||||||||||||
As a result of liquefaction analysis, there is no potential risk of liquefaction at Mawa-Janjira site. | |||||||||||||||||||||||||
On the other hand , there is some protential risks of liquefaction at Paturia-Goalundo site in some depts either before or after scour. | |||||||||||||||||||||||||
Preparatory Study for Preliminary Design on Bridge | |||||||||||||||||||||||||
Bridge Length, which was decided by the river study | |||||||||||||||||||||||||
Paturia-Goalundo= 6.5 km Mawa-Janjira =6.2 km |
|||||||||||||||||||||||||
Applicable Bridge Types over 100m Span Length | |||||||||||||||||||||||||
Concrete Bridge: PC Continuous Box, Extradosed, Cable-stayed | |||||||||||||||||||||||||
Steel Bridge: Steel Continuous Box, Cable-stayed | |||||||||||||||||||||||||
Foundation Types | |||||||||||||||||||||||||
Steel Tubular Driven Piles, Cast-in-situ RC Piles, RC Caissons | |||||||||||||||||||||||||
Cost-Span Relation | |||||||||||||||||||||||||
Minimum cost would be at approx. 200m span length. | |||||||||||||||||||||||||
Favorable Bridge Types and Span Length | |||||||||||||||||||||||||
PC extradosed girder bridge or PC cable-stayed girder bridge would be the most favorable bridge type from the view points of construction cost, maintenance cost, etc. Favorable span lengths will be further examined in a rage of 150m to 250m.
|
|||||||||||||||||||||||||
Initial Environmental Examinations (IEE) | |||||||||||||||||||||||||
Initial Environmental Examination (IEE) was conducted for the two preferred sites to identify the significant environmental impacts | |||||||||||||||||||||||||
A tailor made project specific 6 step template was developed exclusively for this project and applied for two sites | |||||||||||||||||||||||||
For the two sites, most of the impacts are found to be similar | |||||||||||||||||||||||||
There is no significant advantage of one site over other |
|||||||||||||||||||||||||
SIA and Resettlement Issues | |||||||||||||||||||||||||
SIA was conducted for two alternative sites to ascertain the likely impacts of :
|
|||||||||||||||||||||||||
1.
|
Land acquisition | ||||||||||||||||||||||||
2.
|
Local response to the project | ||||||||||||||||||||||||
3.
|
Resettlement needs of the potentially affected persons | ||||||||||||||||||||||||
Survey Results | |||||||||||||||||||||||||
Estimated amount of land to be acquired is almost same (about 1,250 ha ) in both cases
|
|||||||||||||||||||||||||
The number of affected households / structure varies due to differences in population density | |||||||||||||||||||||||||
Current estimate suggests:- | |||||||||||||||||||||||||
Mawa – Janjira | 70,000 to 80,000 | ||||||||||||||||||||||||
Paturia – Goalundo | 40,000 to 45,000 | ||||||||||||||||||||||||
Estimated LA and resettlement cost for M-J site is $39 million, and G-P is $24 million |
|||||||||||||||||||||||||
The Study Team found strong support to the project at both locations | |||||||||||||||||||||||||
Traffic Study and Economic Analysis (Main Work Items) | |||||||||||||||||||||||||
1)
|
Traffic Surveys (Traffic counts, OD Survey) | ||||||||||||||||||||||||
2)
|
Establishment of Future Socioeconomic Framework (Population, GDP, GRDP)
|
||||||||||||||||||||||||
3)
|
Traffic Demand Forecast (Target year 2025) | ||||||||||||||||||||||||
4)
|
Confirmation of Economic Feasibility | ||||||||||||||||||||||||
5)
|
Economic Impacts of the Padma Bridge | ||||||||||||||||||||||||
1)
|
Improvement of Accessibility | ||||||||||||||||||||||||
2)
|
Regional Economic Development | ||||||||||||||||||||||||
3)
|
Formation of International Road Network
|
||||||||||||||||||||||||
Summary of Comparisons of Two Sites from traffic and Economic Point of View
|
|||||||||||||||||||||||||
|
(Beneficiary Population)
Within 3 hours from Dhaka
Within 4 hours from Dhaka
4.5 hours
4.6 hours
2,791,000 (9%)
12,738,000 (42%)
3.6 hours
10,417,000 (35%)
22,247,000 (74%)Density of Feeder Roads
Formation of International Road Network
Regional Economic Development
GDP of Southwest region will increase by 18% (1.2% /year)GDP of Southwest region will increase by 35% (2.3% /year)
Paturia – Goalundo
|
Mawa – Janjira
|
US$ 1,260 million
|
US$ 1,074 million
|
Evaluation Criteria
|
Paturia – Goalundo
|
Mawa – Janjira
|
|
Economic Feasibility |
EIRR |
9.6%
|
16.9%
|
B/C Ratio |
0.71
|
1.81
|
|
NPV (Mil.Taka) |
-9,857
|
23,140
|
|
Regional Development |
Increase of GRDP of Southwest Region |
18% up
(1.2% per year) |
35% up
(2.3% per year) |
Environmental Impact |
Result of IEE |
No big difference
|
|
Social impact and Resettlement Issues | Households requiring relocation |
1,842
|
2,635
|
Community structures affected |
18
|
60
|
|
Total population affected (both direct and indirect) |
40,000-45,000
|
70,000-80,000
|
|
Preliminary RAP cost |
23.7 mil. US$
|
38.79 mil. US$
|
(1) GBW facing to Padma river, or
(2) APW behind the less erodible riverbank (1km apart considering possible erosion during 100 years in future)
To identify the significant environmental impacts Prepare Scope of EIA Prepare a preliminary EMP with cost estimates
Environmental parameters are identified with rational Numerical weightage values are decided with justification Project specific mitigation guidelines are prepared Impact analysis template is used An impact rating template is employed (screening) A Leopold graded impact matrix is applied
There are 8 positive impacts No impacts for 8 parameters There are 24 negative impacts (befort mitigation) There are 14 negative impacts after mitigation (however, impact will be reduced much)
For two sites, most of the impacts are similar More erosion/siltation at Paturia site More water bodies loss at Paturia site More fisheries loss at Paturia site More homestead loss at Mawa site More Income loss at Mawa site More split of communities at Mawa site There is no significant advantage of one site over other
Erosion and siltation (including regional hydrology and drainage congestion) Agricultural / vegetation loss (including plant cutting) Fisheries (including water bodies) Wildlife Land acquisition (including split of communities) Resettlement (including Income loss) Navigation Road accident Air, noise and vibration pollution
A rough cost estimates show that the EMP requirement will be between 2 and 3 million US$ (the EMP cost for the Jamuna Bridge was about 3 million US$)
SIA was conducted for two alternative sites –
(I) Mawa / janjira and (II) Paturia / Goalundo
Planned and carried out to ascertain the likely impacts of -Land acquisition
-Local response to the project
-Resettlement needs of the potential APs
Primary objectives were to -Develop comparative SIA of the two alternatives
-Preliminary Cost estimates
– Develop social/ resettlement criteria for site selection
SIA was not designed for a full scale resettlement study
Conducted over two months (Nov / Dec 2003) Similar ecological and socioeconomic features Methodology adopted include
–
Participatory Rapid Appraisal (PRA)
Focus Group Discussion (FGD)
Meetings with local govt. officials/community leaders
Sample survey using structured questionnaire 200 heads of households were interviewed
•Impacts of Land Acquisition •Estimated amount of LA is same in both sites Mawa / janjira 1272 ha Paturia / Daulatdia 1239 ha impact on households/ population varies –M/J 2,635 hhs (13,204 APs) –P/G 1,842 hhs (8,732 APs) These numbers limited to affected hhs requiring relocation Those affected by loss of land are not Included Jamuna experience – three times higher than those requiring relocation
Loss of residential /commercial structure
Mawa /Janjira – 2635 units
Paturia / Goalundo – 1842 units Close to 80% of the units are made of straw / bamboo, Cl sheet/tile roof – can easily be dismantled and moved Community structures /facilities will also be affected – (I) M/J – 60, and (ii) P/G – 18
Total population affected (directly and indirectly) may run into: Mawa – 70,000-80,000
Paturia – 40,000-45,000 Impacts surely will be greater than currently understood More accurate assessment will be possible only after the site is selected and preliminary design available
Local people are fairly aware of the impacts of LA & Resettlement Impacts Also Informed about donor policies due to the Jamuna and Southwest Road Projects Association and lobby groups have been established at both crossings for selection of their favored sites Strong support to the project – Improved transportation
– Business and new income opportunities
– Control of riverbank erosion
– Opportunities for regional industrial development
Survey included questions with regard to choices and preferred options (i) Mawa / Janjira – 75% of those Interviewed prefer
relocation on their own (self -relocation)
(ii) Paturia / Goalundo – 96% indicated their preferences for self-relocation
Over all, there will be limited demand for resettlement site development Cost estimate – too early for an accurate cost estimate: M-j $39 million; P-G $24 million
SIA data should be treated as indicative of the potential impacts The data is generally in line with the pre-feasibility study A more extensive survey to be carried out for the selected site The detailed information would be crucial for preparing the RAP
Preliminary results shows greater impacts In Mawa-Janjira over
Paturia site Site selection should be more on technical – engineering grounds-future safety of the bridge infrastructure Major Impacts of the project – Irrespective of sites Selection of Final site Is critical to set the next agenda preparation of RAP Task would be to minimize Impact, develop Improved policy for mitigation of adverse Impacts, management and capacity building for resettlement management Experience of the Jamuna and other donor-funded projects will be used In the planning and Implementation of RAP for Padma
the Padma Bridge
(both ways 2003: From Traffic Survey)
Paturia-Goalundo | Mawa-Charjanjat | Cross-Padma Total |
|
Light Vehicle | 572 | 128 |
700
|
Bus | 687 | 227 |
914
|
Truck | 1,217 | 78 |
1,295
|
Total | 2,476 | 433 |
2,909
|
Launch Passenger | 15,559 | 9,126 |
24,685
|
At present, traffic at Mawa is lower than Paturia due to the following reasons: 1) Road condition of NH 8 is now very poor. 2) A narrow approach road to the Mawa ghat. 3) Quality of ferry services at Mawa is lower than Paturia in general. 4) No sufficient parking space for trucks. 5) Two hour river crossing time at Mawa is significantly longer than 35 minutes of Paturia.
Future traffic movement pattern will be drastically changed if the Padma Bridge is constructed at Mawa with following reasons: 1) Improvement of NH 8 (Dhaka – Khulna Road Project by ADB) will be completed by the end of 2004. 2) Direct road link from Dhaka for the largest traffic demands to Khulna and Jcssore. 3) Elimination of two hour crossing time.
1) Vehicle Operating Cost (VOC) Savings 2) Travel Time Cost (TTC) Savings 3) Freight Value Deterioration Savings 4) Ferry Operation Cost Savings 5) Traffic Accident Savings 6) Air Pollution (C02,NOx) Reduction 7) Benefits from Utility Facilities 8) Land Enhancement Benefits
– Evaluation period : 30 years – Opportunity Cost of Capital : 12 % Tentative results: 1) EIRR: Paturia = 9.6% Mawa = 16.9%
where: (R=0.902)
G=Gross Regional Domestic Product/kM2
T=Time to Dhaka from districts in Southwest region (hours)
F=Density of feeder roads (km/kM2)
in
Southwest Region (Growth of GRDP)
Paturia | Mawa | |
SW region | 18% up (1.2%/year) |
35% up (2.3%/year) |
Bangladesh | 4% up | 7% up |
Conclusion
-Natural condition survey such as topographic survey, geotechnical investigation, river
Morphology & mathematical modeling
-Preliminary design of Padma Bridge, approach roads, toll plaza, service area, minor Bridges, underpass, riverbank protection works public utilities etc. -Operation & Maintenance plan of Padma Bridge -Construction plan & procedure of preliminary cost estimate -Environmental study & social impact & resettlement study
The preliminary design in the study would be conducted on the basis of Asian Highway (AH) standards and Roads & Highways Department (RHD) standards. RHD standards are similar to AASHTO standards. Standards adopted by Japan Road Association (JRA), BSI and Indian Road Congress (IRC) would be used as supplementary ones.
Water levels: | ||
Design High Water Level( 100 year return period) | : | DHWL=+7.35m PWD |
Standard High Water Level | : | SHWL=+5.81m PWD |
Mean Water Level | : | MWL=+3.02m PWD |
Standard Low Water Level | : | SLWL=+1.43m PWD |
Water Discharge and velocity: | ||
Design Discharge( 100 year return period) | : | Qd=134,400m3/sec |
Design Water velocity( 100 year return period) | : | Vd=4.6m/sec |
Scour Levels: | ||
Adjacent to Riverbank ( 100 year return period) 300m from riverbank |
: | Zs=-37.56m PWD |
In middle of river( 100 year return period) | : | Zs=-23.63m PWD |
Girder Depths and Bridge lengths | ||||
Bridge Type | Girder Depth at mid span | Aprox. Bridge length | ||
PC Box Girder(Span 160m) | 4.8m | 5,680m | ||
PC Extradosed(Span 180m) | 3.3m | 5,580m | ||
PC Cable Stayed(Span 200m) | 1.8 | 5,480m | ||
Indicative cost by Bridge type without Railway | ||||
Bridge Type | Unit cost/m | Bridge length | Indicative cost | |
PC Box Girder(Span 160m) | US$99,010 | 5,680m | 562 million US$ | |
PC Extradoses(Span 180m) | US$91,620 | 5,580m | 511 million US$ | |
PC Cable Stayed(Span 200m) | US$109,640 | 5,480m | 601 million US$ | |
Reduced river widths by bridge type | ||||
Bridge Type | Number of Piers in the river | Pier width per each | Reduced river width | % Reduced river width |
PC Box Girder(Span 160m) | 34 | 15.0m | 510m | 9.6% |
PC Extradoses(Span 180m) | 31 | 15.0m | 465m | 8.8% |
PC Cable Stayed(Span 200m) | 28 | 16.20m | 454m | 8.6% |
Present river width in 2004=approx. 5,300m | ||||
Total Bridge length | ||||
Padma main bridge | : 5,400m | |||
Left(North) bank Viaduct | : 60m | |||
Right(South) bank Viaduct | : 120m | |||
Total tength | : 5,580m | |||
Specific bridge type and alternatives for preliminary design
Alternative-1(Base case) |
:
|
PC extradosed girder bridge without railway provision |
Alternative-2 |
:
|
PC extradosed girder bridge with cable stayed girder at bridge center portion without railway provision |
Alternative-3 |
:
|
PC extradosed girder bridge with railway provision |
Alternative-4 |
:
|
PC extradosed girder bridge with cable stayed girder at bridge center portion with railway provision |
Alternative-5 |
:
|
PC extradosed girder bridge with minimum investment case |
-12,163 m long approach roads on the both river banks (213 m at left & 11,950 m at right banks) – 6 m width service road on both sides along the approach road & 2m lower than that of the approach road -No of minor bridges on approach roads-6nos (total length=1000m) -No of culverts (for underpasses for crossing RHD/LGED road) on approach roads-13nos